Interconnection Queue Status

Section 17.9.573.12(L) of the amended Community Solar Rule, published by the New Mexico Public Regulation Commission on 9/9/2026, directs each utility to “provide a report to the program administrator on the status of the community solar project interconnection queue as of January 1, April 1, July 1, and October 1, no later than the 15th of each of those months, respectively. Such reports must include information on the status of each scored community solar project that has made application with respect to the following data, which the program administrator must post publicly to the program website.”

The following is the interconnection queue status of projects in the New Mexico Community Solar Program as reported by the utilities as of 10/1/2026.

EPE

Bid ID Project Name Project Location/Circuit ID Subscriber Organization Project Size (MWac) Interconnection Review Status PTO Date Withdrawn Date
255SLT Las CrucesLas CrucesPluma LLC4.975operational12/8/2025N/A
326USS Jornada Solar LLCLas CrucesLos Ebanistas, Inc.4.995Projects in Facilities Study-Eng Design12/21/2026N/A
373Chaparral 1ChaparralSVOE, LLC5.000Projects in Facilities Study-Eng Design4/30/2027N/A
219The Wings for Life Community Solar Project (State Land 3)Las CrucesAffordable Solar Silver City, LLC4.975operational12/29/2025N/A
188Lower Rio Grande Solar, LLCVadoLower Rio Grande Solar, LLC5.000Projects in Facilities Study-Eng DesignTBDN/A
176Bent Bow Solar, LLCSalemBent Bow Solar, LLC4.980operational12/8/2025N/A

SPS

Bid ID Project Name Project Location/Circuit ID Subscriber Organization Project Size (MWac) Interconnection Review Status PTO Date Withdrawn Date
265Clovis Concrete NorthClovisPluma Solar Clovis 1, LLC3.450PTO4/3/2026N/A
270Curry Road NorthClovisPluma Solar Clovis 2, LLC3.000PTO12/4/2025N/A
421Oasis Sol Community Solar GardenPortalesCSolPower LLC4.975Interconnection AgreementQ4 2027 - Q2 2028N/A
380Clovis IVClovisSVOE, LLC5.000Interconnection AgreementQ4 2027 - Q2 2028N/A
331Ben ThomasRoswellThe Cabinet Shoppe Inc.1.950PTO3/3/2026N/A
404Portales IPortalesSVOE, LLC2.750Interconnection AgreementQ4 2027 - Q2 2028N/A
305Cannon SolarClovisCannon Solar, LLC4.950Interconnection AgreementQ4 2027 - Q2 2028N/A
200Dougherty (Rayroux)CarlsbadPPC New Energy LLC4.950Design and ConstructionQ3 2027 - Q2 2028N/A
221The WESST Community Solar Project (Xcel Site 1)RoswellAffordable Solar Silver City, LLC4.975PTO2/27/2026N/A
178Gallagher SolarRoswellGallagher Solar LLC2.700Interconnection AgreementQ1 2028 - Q3 2028N/A
435USS Millen Solar LLCHobbsLos Ebanistas, Inc.4.995Interconnection AgreementQ4 2027 - Q2 2028N/A

PNM

Bid ID Project Name Project Location/Circuit ID Subscriber Organization Project Size (MWac) Interconnection Review Status PTO Date Withdrawn Date
260SLT OteroAlamorgordo / A10083Pluma Solar LLC3.500Interconnection AgreementFeb 2027N/A
220SLT HildalgoLordsburg / LD1000Pluma Solar LLC3.750Permission to Operate (PTO)6/11/2026N/A
291SLT GrantSilver City / SL0017Pluma Solar LLC4.975Permission to Operate (PTO)9/24/2026 (agreed to operate at partial capacity 2.250 MW)N/A
286ReynoldsTularosa / TULA13Pluma Solar LLC5.000Permission to Operate (PTO)1/7/2026N/A
285PINOLas Vegas / GALL13Pluma Solar LLC4.975Permission to Operate (PTO)10/28/2025N/A
416Trigo Sol CS GardenBelen / TOME11Sunshare/Csol3.400Interconnection Agreement12/11/2026N/A
217The Homewise Project (State Land 2)Albuquerque / ENCHillS 13Affordable Solar4.975Permission to Operate (PTO)8/31/2026N/A
215Global Give a Book (site 1)Los Lunas / MANZ12Affordable Solar4.975Permission to Operate (PTO)11/19/2025N/A
439Gonzo SolClayton / VNBU12Sunshare/Csol4.975Interconnection Agreement12/1/2026N/A
191Atari SolarAlamorgordo / A10089Atari Solar4.950Interconnection AgreementApr 2027N/A
443USS Meadow Lake Solar LLCLos Lunas / ELCE12US Solar Corp3.000Interconnection Agreement12/29/2026N/A
227NeudeckerSilver City / SL0017PCC New Energy Eguity2.250WithdrawnWithdrawn5/8/2026
7Locker 505 project (site 2)Rio Rancho / VERA22Affordable Solar4.975Permission to Operate (PTO)12/18/2025N/A
213Cuidando Los Ninos (Site 4)Belen / FIST13Affordable Solar4.975Permission to Operate (PTO)9/24/2025N/A
310Gorman OteroLos Lunas / MANZ12Affordable Solar3.600Facilities Study/Engineering DesignJan 2027N/A
207Central NMCC Project (site 4)Belen / JARA11Affordable Solar4.975Permission to Operate (PTO)12/15/2025N/A
424Rockhound SolDeming / HOND11Sunshare/Csol4.000Permission to Operate (PTO)6/12/2026N/A
414Juniper SolSanta Fe / COLI11Sunshare/Csol4.975Permission to Operate (PTO)7/1/2026N/A
422Raven SolLordsburg / LD1000Sunshare/Csol4.975Interconnection Agreement12/21/2026N/A
437USS Fletcher LLCLordsburg / LDO318US Solar Corp1.665Interconnection Agreement12/14/2026N/A
441USS Gold LLCDeming / HERM14US Solar Corp4.255Interconnection Agreement12/7/2026N/A
438USS Florida MountainDeming / HOND12USS Solar Corp4.625Interconnection AgreementAug 2028N/A
442USS Hermanas LLCDeming / HERM11USS Solar Corp3.330Interconnection Agreement12/18/2026N/A
381Tularosa 1Tularosa / TULA14SVOE, LLC2.875Facilities Study/Engineering DesignMar 2027N/A
377Tularosa 3Tularosa / TULA14SVOE, LLC4.500FacilitiesStudy/Engineering DesignMar 2027N/A
374Tularosa 4Tularosa / TULA12SVOE, LLC2.750Facilities/Engineering DesignJuly 2027N/A
379Tularosa 2Tularosa / TULA13SVOE, LLC4.750Facilities Study/Engineering DesignMar 2027N/A
383Los Lunas ILos Lunas / ELCE14SVOE, LLC4.000WithdrawnWithdrawn6/12/2026
198BergmanDeming / HOND11PPC New Energy Equity4.650Facilities Study/Engineering DesignFeb 2027N/A
360Lake JodyDeming / Gold 11Prospertiy Works2.100Interconnection AgreementMay 2027N/A
195Donaldson IIDeming / SL0017PPC New Energy Equity4.550Scoping meetingAug 2027N/A
359Boston HillLordsburg / Unknown-No application yetProspertiy Works1.750Waiting on Interconnectiion application to be submittedOct 2027N/A